Be it enacted by the People of the State of Maine as follows:

 
Sec. 1. 5 MRSA §1746, first ¶ is amended to read:

 
In Except as provided in section 1746-A, in any contract
awarded for any public improvement the State shall withhold 5% of
the money due the contractor until the project under the contract
has been accepted by or for the State, except that when the
contract has been substantially completed the State may, upon
request, further reduce the amounts withheld if it deems
determines it desirable and prudent.

 
Sec. 2. 5 MRSA §1746-A is enacted to read:

 
§1746-A.__Retention of part of contract payment for state and

 
major school construction projects

 
This section governs the retention of part of the contract
payment for public improvement projects as defined in subsection
1.__This section does not prevent the withholding of payment to
cover good faith claims as provided in Title 10, section 1118.

 
1.__Definitions.__As used in this section, unless the context
otherwise indicates, the following terms have the following
meanings.

 
A.__"Nonperformance" includes, but is not limited to,
defects in workmanship or materials, failure to perform all
the work specified or delay by the general contractor or
subcontractor that causes adverse financial consequences.

 
B.__"Owner" means the State, a school administrative unit or
a school building committee having an interest in real
property on which a public improvement project is or will be
constructed.

 
C.__"Public improvement project" means:__the construction,
major alteration or repair of buildings or public works
owned or leased or hereafter constructed, acquired or leased
by the State or any department, officer, board, commission
or agency of the State when that construction, major
alteration or repair of buildings or public works is in
excess of $1,000,000 in value; or the construction, major
alteration or repair of school buildings that is in excess
of $1,000,000 in value and for which state school
construction aid is paid.

 
D.__Punch list" means a list made near the completion of
work that indicates minor items to be corrected or work to
be performed by the general contractor or subcontractor in
order to complete the work as specified in the contract
documents.