| The bill applies to state construction projects over |
$1,000,000 in value and to school construction projects over |
$1,000,000 in value and for which state aid is received. The |
bill limits the retention of contract payments on those public |
improvement construction projects to line items in the project |
contract and to situations in which unsatisfactory progress has |
been made by a contractor or subcontractor. In those cases, up |
to 5% of the payment due under the project contract may be |
withheld until all contract requirements for the line item have |
been completed. Following completion of a line item, any |
retained payments must be paid promptly. At the end of a |
project, the value of punch list and incomplete items may be |
retained as well as withholding to cover good faith claims of the |
owner, including claims for unsatisfactory progress on the |
project. Over the course of the project, the owner makes the |
determination of how much of the payment due will be retained up |
to the 5% limit and as to whether satisfactory progress has been |
made on the project. |