| Sec. 4. Reimbursement. Central Maine Power Company shall reimburse |
| customers who were charged for line extensions pursuant to the |
| revised terms and conditions approved by the commission in its |
| order of November 10, 1999 in Docket Number 99-042. Within 30 |
| days of the effective date of this Act, the Public Utilities |
| Commission shall open a proceeding to establish the mechanism by |
| which Central Maine Power Company will reimburse customers. |
| Costs incurred by Central Maine Power Company to reimburse |
| customers pursuant to this section, to pay for line extensions |
| and to reimburse customers pursuant to section 3 of this Act, are |
| just and reasonable expenses for rate-making purposes. The |
| commission shall determine the manner in which these costs may be |
| recovered by Central Maine Power Company through rates. The |
| commission may issue appropriate orders to accomplish the |
| purposes of this section. |