| Sec. 4. Reimbursement. Central Maine Power Company shall reimburse |
customers who were charged for line extensions pursuant to the |
revised terms and conditions approved by the commission in its |
order of November 10, 1999 in Docket Number 99-042. Within 30 |
days of the effective date of this Act, the Public Utilities |
Commission shall open a proceeding to establish the mechanism by |
which Central Maine Power Company will reimburse customers. |
Costs incurred by Central Maine Power Company to reimburse |
customers pursuant to this section, to pay for line extensions |
and to reimburse customers pursuant to section 3 of this Act, are |
just and reasonable expenses for rate-making purposes. The |
commission shall determine the manner in which these costs may be |
recovered by Central Maine Power Company through rates. The |
commission may issue appropriate orders to accomplish the |
purposes of this section. |