LD 633
pg. 1
An Act To Provide for Local Approval of Existing or Former Hydropower Projects ...
Download Bill Text
LR 1387
Item 1
Be it enacted by the People of the State of Maine as follows:
Sec. 1. 38 MRSA §635-C
is enacted to read:
§635-C.__Local approval
1.__Authority to override department's decision.__
A
municipality in which a hydropower project is located may
override the department's decision pursuant to section 635 at
a town meeting specially called for this purpose if:
A.__The hydropower project was built prior to 1952;
B.__The hydropower project is or will be rebuilt to a
height of 15 feet or less; and
C.__The hydropower project does not require a license from
the Federal Energy Regulatory Commission or a federal
exception for a hydropower project.
2.__Standards.__
A project that is approved by a municipality
pursuant to this section must meet all standards required by
the department.
SUMMARY
This bill provides municipalities with the authority to
override a decision made by the Department of Environmental
Protection regarding construction or reconstruction of a
hydropower project.
Top of Page
Additional Information
Amendments
Public Hearings
Committee Information
Other Documents
Work Sessions
Title & Section