| 1.__Basis for variance.__The board may grant a variance from | | the sand supply standard in section 480-D, subsection 7 for the | | following only: |
|
| | | A.__Reconstruction or replacement of a building located in | | a V-zone, as described in section 480-E, subsection 9, due | | to involuntary destruction by fire or other cause, except | | for an ocean storm; or |
|
| | | B.__Height restrictions for new structures or additions to | | existing structures for the purpose of raising an existing | | building above the flood elevation, provided the increase | | in height is no more than the minimum necessary to meet | | flooding requirements. |
|
| | | 2.__Requirements.__In order to obtain a variance, the | | applicant must demonstrate, by clear and convincing evidence, | | that: |
|
| | | A.__There is no feasible alternative to the proposed | | variance; |
|
| | | B.__Because of unusual design characteristics or site | | conditions, the project will be consistent with the intent | | of the board; |
|
| | | C.__If the variance is granted, the project will not cause | | harm to real or personal property not owned by the | | applicant; and |
|
| | | D.__Even if the proposed variance is granted, all other | | statutory criteria set forth in section 480-D will be met. |
|
| | | This bill prohibits seawall construction and enlargement; | | prohibits reconstruction of buildings in the sand dune system | | damaged by more than 50% by a storm; prohibits construction of | | new buildings in the frontal dune; and authorizes the Board of | | Environmental Protection to grant variances from sand supply | | standards. |
|
|