maximum height on the beach the rush of water reaches and the | still water level. |
|
| | 14.__X-zone.__"X-zone" means an area between an A-zone and | the presumed high-water mark of a 500-year flood.__This zone | also includes areas of 100-year shallow flooding where water | depths are less than one foot or the flooded area is less than | one acre in size. |
|
| | Sec. 11. 38 MRSA §480-C, sub-§4 is enacted to read: |
|
| | 4.__Review not required.__This subsection clarifies which | activities in coastal sand dune systems do not require | approval pursuant to this article. |
|
| A.__The following activities have minimal impact and do | not require a permit under subsection 2: |
|
| (1) Construction of a walkway or path on an area of a | lot that has already been developed; |
|
| (2)__Removal of debris from a beach, as long as | little or no sand is removed with the debris; |
|
| (3)__The addition of loam, up to 3 inches in depth, | to maintain an existing lawn; |
|
| (4)__Removal of sand from lawns, walkways, roads, | driveways, parking areas and buildings, as long as | the sand is placed back into the coastal sand dune | system without disturbing beach vegetation.__Sand | placed on the beach must be spread out to a height no | greater than 3 inches above the existing beach grade; |
|
| (5) The placement of an open fence in the coastal sand | dune system to keep pedestrian traffic off dune | vegetation or away from shore bird nesting or | breeding areas; |
|
| (6) The replacement of an existing partial or full | foundation with a post or piling foundation that | complies with the requirements of section 480-AA, | subsection 4 and section 480-BB, subsection 5 and | allows for the free movement of sand and water and | remains in the existing footprint; and |
|
| (7)__Construction of a municipal sewer or storm water outfall | pipe that is buried and that has received approval from the | department under department rule, |
|
|