| | 1. Penalties. The commission shall require an investor-owned | transmission and distribution utility to divest an affiliated | competitive provider if the commission determines in an | adjudicatory proceeding that: |
|
| A. The distribution utility or an affiliated competitive | provider has knowingly violated section 3205 or section 3206 | or any rule adopted by the commission pursuant to those | sections; and |
|
| B. The violation resulted or had the potential to result in | substantial injury to retail consumers of electric energy or | to the competitive retail market for electric energy. |
|
| The commission may impose administrative penalties of up to | $100,000 for a violation of section 3205 or section 3206 or any | rule adopted by the commission pursuant to those sections. Each | day of a violation constitutes a separate offense. In addition, | the commission may require disgorgement of profits or revenues | realized as a result of a violation of section 3205 or section | 3206 or any rule adopted by the commission pursuant to those | sections. Penalties collected by the commission under this | section must be deposited in the Public Utilities Commission | Reimbursement Fund under section 117. |
|
| | Sec. 31. 35-A MRSA §4512, sub-§1, as enacted by PL 1987, c. 141, Pt. | A, §6, is repealed. |
|
| | Sec. 32. 35-A MRSA §4512, sub-§2, as enacted by PL 1987, c. 141, Pt. | A, §6, is amended to read: |
|
| | 2. Damages. In addition to the forfeiture provided in | subsection 1 administrative penalty imposed pursuant to this | Title, a natural gas pipeline utility that fails to comply with | an order of the commission shall reimburse any person whose | property is damaged as a result of the failure for the amount of | the property damage; and be liable in double damages for any | injury resulting to a person from the failure. |
|
| | Sec. 33. 35-A MRSA §4515, as enacted by PL 1987, c. 141, Pt. A, §6, | is amended to read: |
|
| §4515. Cease and desist orders |
|
| | A The commission may order a natural gas pipeline utility to | cease and desist from operating or acting in violation of a | statute or rule or order of the commission may be enjoined from | the operation or action upon complaint addressed to the Superior | Court and brought by the commission. Whenever practicable, the | commission shall notify a natural gas pipeline utility against |
|
|