| 2.__Retainage.__In any contract awarded for a public |
| improvement, the owner of a public improvement may retain 5% of |
| the money due the contractor until substantial completion of the |
| work.__At substantial completion, the owner and the contractor |
| shall inspect the work and prepare a punch list.__The owner may |
| thereafter withhold for defective or incomplete work only those |
| funds that are sufficient to account for 1.5 times the value of |
| punch list work.__As punch list work is completed, the retainage |
| held by the owner must be correspondingly reduced.__Funds may not |
| be retained in anticipation of warranty claims but may be |
| retained as directed by the contractor's surety or as necessary |
| to account for liquidated damages or other contract defaults as |
| determined by the designer. |