(3) A date or schedule indicating when approvals must be | obtained; and |
|
| (4) Storm water quantity and quality standards for | storm water management systems. |
|
| C. The owner or operator of a site designated as a | significant existing source shall apply to the department | for approval of a storm water management system. |
|
| D.__"Significant existing source" does not include: |
|
| (1)__Types of sources or activities described in | subsection 7; |
|
| (2)__The developed area of a facility required to meet | ongoing storm water management standards pursuant to a | storm water general or individual permit issued | pursuant to section 413; and |
|
| (3)__A municipal storm water conveyance system unless | the storm water pollution originates with the | conveyance system. |
|
| | Sec. 8. Transition. Prior approval is required pursuant to the | Maine Revised Statutes, Title 38, section 420-D if a person | constructs, or causes to be constructed, a project that includes | one acre or more of disturbed area on or after the effective date | of this Act. |
|
| | 1. If a person has a project that required approval prior to | the effective date of this Act, the project continues to require | approval on and after the effective date of this Act. |
|
| | 2. If a person has a project that did not require approval | prior to the effective date of this Act, and the person proposes | to construct or cause to be constructed a project that includes | one or more acres of disturbed area on or after the effective | date of this Act, then approval is required. Only the | construction on or after the effective date of this Act requires | prior approval. |
|
| | 3. A disturbed area of less than one acre continues to be | counted toward the one-acre permit threshold under this section | following permanent stabilization to the extent it is considered | developed area as defined in rules adopted by the Department of | Environmental Protection. |
|
|