An Act To Facilitate Testing and Demonstration of Renewable Ocean Energy Technology
PART A
Sec. A-1. 38 MRSA §344-A, first ¶, as amended by PL 2007, c. 661, Pt. B, §6, is further amended to read:
The commissioner may enter into agreements with individuals, partnerships, firms and corporations outside the department, referred to throughout this section as "outside reviewers," to review applications or portions of applications submitted to the department. The commissioner has sole authority to determine the applications or portions of applications to be reviewed by outside reviewers and to determine which outside reviewer is to perform the review. When selecting an outside reviewer, all other factors being equal, the commissioner shall give preference to an outside reviewer who is a public or quasi-public entity, such as state agencies, the University of Maine System or the soil and water conservation districts. Except for an agreement for outside review regarding review of an application for a wind energy development as defined in Title 35-A, section 3451, subsection 11 or , a certification pursuant to Title 35-A, section 3456 , or a general permit pursuant to section 480-HH or section 636-A, the commissioner may enter into an agreement with an outside reviewer only with the consent of the applicant and only if the applicant agrees in writing to pay all costs associated with the outside review.
Sec. A-2. 38 MRSA §480-HH is enacted to read:
§ 480-HH. General permit for offshore wind energy demonstration project
(1) Up to 3 meteorological towers per wind energy turbine proposed;
(2) One submerged utility line that is sized to transmit:
(a) An amount of electricity less than or equal to that produced by the offshore wind energy demonstration project; or
(b) Up to 25 megawatts of electricity if the line is intended to serve multiple offshore wind energy demonstration projects located within the Maine Offshore Wind Energy Research Center and the department has not previously granted approval for such a submerged utility line pursuant to this section; and
(3) A wave energy test project.
(1) Is proposed as part of an offshore wind energy demonstration project and is designed and sited to test production of electricity from wave energy in conjunction with and in a manner that complements electricity produced by an offshore wind energy turbine;
(2) Employs up to 2 wave energy converters, each of which may use different technology, that the applicant certifies are designed for use in the ocean and are not in use elsewhere in the Gulf of Maine for commercial production, for the primary purpose of testing and validating the overall design of the converter and its related systems, subsystems or components; and
(3) May include one or more of the following additional elements:
(a) A mooring or anchoring system; and
(b) An ocean sensor package.
(1) A plan view drawing of the entire project area that shows, with geographic positioning system references, the proposed location of the generating facilities and all other project elements, including but not limited to any submerged utility line or meteorological tower;
(2) A narrative description of the proposed activities and methods for construction, operation and removal of the offshore wind energy demonstration project that addresses on-site management of fuels, lubricants and other materials used for project operations or maintenance;
(3) A scale drawing that shows the design and location of the proposed mooring or anchoring system;
(4) A drawing showing the location of the submerged utility line, if any, and plans for its construction in compliance with the permit by rule standards regarding construction of a submerged utility line established in rules adopted by the board; and
(5) A drawing showing the proposed location of each wind turbine in relation to any other offshore wind energy demonstration project within 10 kilometers of the proposed project and written verification that the project will not interfere with the operation of any such previously approved project.
(1) Describes existing information regarding commercial fishing and other existing uses in the project area; and
(2) Describes, based on a field investigation, the marine resources, including benthic communities, in the marine waters and on the submerged lands and immediately adjacent areas in, on or over which the applicant proposes to locate any mooring, anchoring system, meteorological tower, ocean sensor package, submerged utility line or other project element that is secured to the seabed;
(1) A detailed description of the methods and equipment that will be used for monitoring fish and wildlife behavior and activity in the vicinity of the project;
(2) A detailed description of how the fish and wildlife monitoring data will be analyzed and provided to the department in electronic format, with specific criteria by which to evaluate adverse effects;
(3) A detailed implementation schedule, including the frequency and timing of data recovery, maintenance of the monitoring equipment and quarterly reporting to the department;
(4) A detailed monitoring schedule that considers ocean conditions, seasonal variations in species' presence or absence and other pertinent biological factors;
(5) Provisions for identifying and implementing remedial measures if monitoring identifies any adverse changes in fish or wildlife behavior or use of ocean habitats;
(6) A detailed description of the methods and equipment that will be used to determine and monitor ambient noise levels, electromagnetic fields and noise associated with project construction and subsequent operations and the effectiveness of any devices that are proposed to avoid and minimize the potential for related foreseeable adverse effects, if any; and
(7) Provisions for filing an annual report with the department describing the monitoring results and any recommendations for modifying the generating facilities or other project elements, or commencing the approved project removal plan, if necessary to minimize adverse effects on natural resources identified pursuant to plans required under this section. Thirty days prior to submission of the report to the department, the applicant shall provide a draft of the report to the Department of Marine Resources, the Department of Inland Fisheries and Wildlife, the Department of Conservation, the United States Fish and Wildlife Service and the National Marine Fisheries Service and shall include in the annual report any comments from those agencies and the applicant's responses to them;
(1) A geo-located navigation and underwater activity exclusion zone boundary around the proposed generating facilities, anchoring system, submerged utility line and other project elements, if any. The exclusion zone must be designed to minimize potential conflicts with other existing uses in the area and may be no larger than the applicant demonstrates is necessary to achieve the purposes of the project;
(2) Marking the extreme corners of the exclusion zone with lights, buoys or other indicators sufficient to warn vessels of the above-water and underwater project elements and the boundaries of the exclusion zone during both day and night;
(3) Marking the generating facilities with fog signals, low-intensity navigation lights, hazard marking lights or other aids to navigation and painting and lighting the generating facilities in a way that considers the aesthetic resources of the project area as well as the safety of the public and project facilities and meets applicable Federal Aviation Administration guidelines and United States Coast Guard requirements;
(4) Procedures to ensure the safety of the public near the project area; and
(5) A description of monitoring for and actions the applicant will take to prevent and address an emergency that specifies: procedures the applicant will take during an emergency, including but not limited to immediate shutdown; a protocol for coordination with and reporting an emergency to local, state and federal agencies; contingency measures to modify operations to address reasonably foreseeable emergency conditions; and a schedule for annual testing of emergency equipment, including the project's emergency shutdown system;
(1) Removal of the project in its entirety from all project lands and waters, except for any part of the project regarding which the applicant provides the department substantial evidence of plans for continued beneficial use, including but not limited to an executed lease of state-owned submerged lands, as applicable, or for partial removal or other modification adequate to avoid foreseeable adverse effects on natural resources and existing uses;
(2) Minimizing seabed disturbances and suspended sediments during removal of any underwater facilities;
(3) Monitoring the effects of the removal activities on species listed as threatened or endangered species in Title 12, section 6975 or Title 12, section 12803, subsection 3 and marine resources both during and subsequent to completion of removal activities;
(4) An implementation schedule that provides for all removal and restoration activities to be completed within one year of the expiration date of the general permit pursuant to subsection 9;
(5) An estimate of the total project removal cost, without regard to salvage value of the equipment, and the net project removal cost, prepared by a licensed professional engineer; and
(6) Written evidence and certification that the applicant has posted and will maintain funds for project removal in an amount equal to the net project removal cost, except that at no point may such funds be less than 25% of the total project removal cost. The applicant shall post and maintain project removal funds with a bonding company or federal-chartered or state-chartered lending institution that is authorized to do business in the State and chosen by the applicant and considered acceptable by the department posting the financial security. Project removal funds may be in the form of a performance bond, surety bond, letter of credit, corporate guarantee or other form of financial assurance that the department considers adequate to ensure funds posted pursuant to this paragraph will remain inviolate and available for project removal if the applicant ceases to exist, declares bankruptcy or becomes insolvent or otherwise unable to finance the project removal plan required under this paragraph;
A municipality may not enact or enforce any land use, zoning or other standard, conditions or requirement regarding an offshore wind energy demonstration project located within the municipality that is stricter than standards, conditions or requirements of this section. The municipality has the burden of proof regarding the location of the project in relation to its boundaries. Any action by the municipality regarding its authorization to site, construct or operate an offshore wind energy demonstration project must be taken within 60 days of the grant of a general permit under this section or within 30 days of the granting of a permit modification pursuant to subsection 13.
PART B
Sec. B-1. 12 MRSA §1862, sub-§2, ¶F is enacted to read:
PART C
Sec. C-1. 12 MRSA §1868 is enacted to read:
§ 1868. Identification of offshore wind energy test areas
PART D
Sec. D-1. 12 MRSA §685-B, sub-§1-A, ¶B, as amended by PL 2001, c. 402, §4, is further amended to read:
Sec. D-2. 12 MRSA §685-B, sub-§1-A, ¶C, as enacted by PL 2001, c. 402, §5, is amended to read:
Sec. D-3. 12 MRSA §685-B, sub-§1-A, ¶D is enacted to read:
Sec. D-4. 12 MRSA §685-B, sub-§1-A, ¶E is enacted to read:
Sec. D-5. 38 MRSA §634-A is enacted to read:
§ 634-A. Administering agency
Sec. D-6. 38 MRSA §635-B, as amended by PL 1989, c. 890, Pt. A, §40 and Pt. B, §186, is further amended to read:
§ 635-B. Procedures for water quality certification
Issuance of a water quality certificate required under the United States Federal Water Pollution Control Act, Section 401, is coordinated for the applicant under this subarticle by the Commissioner of Environmental Protection. The issuance of a water quality certificate is mandatory in every case where the department approves an application for a permit or general permit under this subarticle. An application for a tidal energy demonstration project under section 636-A that is accepted as complete by the department serves as an application for water quality certification for the proposed project pursuant to the Federal Water Pollution Control Act, Section 401, 33 United States Code, Section 1341. The department shall issue or deny certification at the same time it approves or disapproves the proposed project. If issued, the certification must state that there is a reasonable assurance that the project will not violate applicable water quality standards. The coordination function of the department with respect to water quality certification does not include any proceedings or substantive criteria in addition to those otherwise required by this subarticle.
Sec. D-7. 38 MRSA §636, sub-§5, as enacted by PL 1983, c. 458, §18, is amended to read:
Sec. D-8. 38 MRSA §636-A is enacted to read:
§ 636-A. General permit for tidal energy demonstration project
(1) Has a total installed generating capacity of 5 megawatts or less; and
(2) Is proposed for the primary purpose of testing tidal energy generation technology, which may include a mooring or anchoring system and transmission line, and collecting and assessing information on the environmental and other effects of the technology.
(1) A description of the waters of the State in which the proposed project will be located;
(2) A description of proposed project facilities and operation;
(3) Site-specific information regarding the physical environment in which the project is proposed to be located and the anticipated environmental effects of the proposed project;
(4) A plan for monitoring the environmental effects of the project through the term of the general permit;
(5) A plan for safeguarding the public and environmental resources through the term of the general permit;
(6) A plan for removing the project after the termination of the general permit unless the applicant is pursuing a license for a commercial tidal power project at the site; and
(7) Documentation that, in developing the application, the applicant has consulted with the appropriate local, state and federal resource agencies, as well as local governments, Indian tribes, nongovernmental organizations and members of the public likely to be interested in the project;
summary
This bill contains several provisions to facilitate research and development and demonstration of renewable ocean energy technologies.
Part A streamlines state permitting of offshore wind energy demonstration projects by creating a general permit administered by the Department of Environmental Protection for qualified projects located in specific offshore areas identified under Part C of the bill.
Part B streamlines the process for issuance of a state submerged lands lease for an offshore wind energy demonstration project granted a general permit in accordance with Part A of the bill or a tidal energy demonstration project granted a general permit under Part D of the bill.
Part C calls for a public process to identify up to 5 specific offshore areas in which an offshore wind energy demonstration project may be granted a general permit as provided in Part A of the bill based on consideration of potential effects on natural resources and existing uses, community support and other factors. Part C further provides for designation of one of these areas as the Maine Offshore Wind Energy Research Center to facilitate offshore wind energy-related research and development conducted by or in cooperation with the University of Maine System.
Part D streamlines state permitting of tidal energy demonstration projects by creating a general permit administered by the Department of Environmental Protection for projects eligible for a pilot project license from the Federal Energy Regulatory Commission.