129th MAINE LEGISLATURE |
|
|
LD 2164 |
|
LR 3308(01) |
|
|
|
Resolve, To Reject
the New England Clean Energy Connect Transmission Project |
|
Fiscal Note for
Initiated Bill |
|
Committee: Not Referred |
|
Fiscal Note Required: No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Note |
|
|
|
|
|
|
|
Minor cost increase - Other Special Revenue Funds |
|
|
|
|
|
|
|
Fiscal Detail
and Notes |
|
|
|
|
|
|
This resolve
directs the Public Utilities Commission (PUC) to amend a previously issued
“Order Granting Certificate of Public Convenience and Necessity and Approving
Stipulation” entered by the PUC on May 3, 2019 for the New England Clean
Energy Connect transmission project. Requiring the amended order to find that
the construction and operation of the transmission project are not in the
public interest and that there is not a public need for it, and requiring
denial of a certificate of public convenience and necessity for the project,
may extend or reopen the deliberative process of the PUC related to the
project. Any additional costs to the PUC as a result of this initiative are
within the scope of activities budgeted by the PUC and are not anticipated to
require supplemental appropriations or allocations. |
|
|
|
|
|
|
|