Title 35-A: PUBLIC UTILITIES
Part 3: ELECTRIC POWER
Chapter 36: COMMUNITY-BASED RENEWABLE ENERGY
§3621

§3610. Project deadline; completion deadline

The commission may not issue an order after December 31, 2015 directing an investor-owned transmission and distribution utility to enter into a long-term contract under this chapter nor allow a consumer-owned transmission and distribution utility to enter into a long-term contract under this chapter. All community-based renewable energy projects that have been selected for a long-term contract must become operational and commence generating electricity by December 31, 2018.   [PL 2015, c. 232, §4 (NEW).]
SECTION HISTORY
PL 2015, c. 232, §4 (NEW).
The Revisor's Office cannot provide legal advice or interpretation of Maine law to the public.
If you need legal advice, please consult a qualified attorney.
Office of the Revisor of Statutes · 7 State House Station · State House Room 108 · Augusta, Maine 04333-0007
Data for this page extracted on 1/07/2025 11:10:17.
Maine Government
Legislature • Executive • Judicial • Agency Rules
Visit the State House
Tour Guide • Accessibility • Security Screening • Directions & Parking
Email
Office of the Revisor of Statutes