     Sec. 1. 5 MRSA §1743, as amended by PL 1989, c. 596, Pt. N, §3, is repealed and the following enacted in its place:

§1743. Public improvement construction contracts

     The Department of Administrative and Financial Services through the Bureau of General Services shall award a contract in accordance with this section for any public improvement that the State or any of its agencies hold in fee involving a total cost in excess of $100,000, except contracts for professional, architectural and engineering services. The bureau may reject any public improvement bid, qualification package or proposal when it determines that to do so is in the best interests of the State. The contract must be awarded by competitive bid as provided in subsection 2 or by the bid method provided in subsections 3 to 7 for alternative methods of project delivery.

     1. Definitions. As used in this section, unless the context otherwise indicates, the following terms have the following meanings.

     2. Competitive bids. A public improvement contract may be awarded under a system of competitive bidding in accordance with this Part and such other conditions as the Governor may prescribe.

     3. Alternative methods of project delivery. As an alternative to the competitive bid method provided in subsection 2, a public improvement contract may be undertaken using the construction-manager-advisor, construction-manager-at-risk or design-build method of construction.

     4. Alternative Delivery System Review Panel. The director shall establish the Alternative Delivery System Review Panel to advise the director in developing alternative project delivery policies, procedures and rules and in selecting public improvement projects for construction under an alternative delivery method.

     5. Design-build method. The design-build method must be consistent with guidelines approved by a national architect, general contractor or design-build organization or a combined or modified version of the guidelines approved by those entities, with the final design-build procedures and documents to be determined at the discretion of the bureau. The bureau may prequalify design-build teams using criteria that must include at a minimum those set forth in section 1747 and may also include additional criteria considered appropriate by the director.

     6. Construction-manager-at-risk method. The construction-manager-at-risk method must be consistent with the concepts set forth in a standard form of agreement between an owner and a construction manager when the construction manager is also the constructor as established by national architect or general contractor organizations. The final procedures and documents for this method of delivery are determined at the discretion of the director.

     7. Construction-manager-advisor method. The construction-manager-advisor method must be consistent with the standard scope of services employed by the bureau in public improvement projects.

     8. Owner's representative. The bureau may employ a qualified individual to represent the owner on any public improvement project awarded under the competitive bid process provided in subsection 2 or an alternative method of project delivery provided in subsection 3. Owner's representative services must be consistent with the standard scope of services employed by the bureau. The services of the owner's representative must be procured in a manner consistent with the bureau's rules governing selection of architects and engineers or with policies and procedures adopted by rule of the bureau with the advice of the review panel.

     Sec. 2. 5 MRSA §1747, sub-§3, as amended by PL 1997, c. 295, §1, is further amended to read:

     3. Insufficient resources. If, in the opinion of the director, there is evidence the contractor does not have sufficient resources to successfully complete the work; or. The director may require additional information about the contractor's resources, including identification of major claims or litigation pending and whether the contractor has sought protection under the bankruptcy laws in the past 5 years. That information is confidential and not subject to disclosure under Title 1, chapter 13, subchapter I;

     Sec. 3. 5 MRSA §1747, sub-§4, as enacted by PL 1989, c. 483, Pt. A, §20, is amended to read:

     4. Misconduct. If the contractor has been convicted of collusion or fraud or any other civil or criminal violation relating to construction projects. ;

     Sec. 4. 5 MRSA §1747, sub-§§5, 6 and 7 are enacted to read:

     5. Safety record. If, in the opinion of the director, there is evidence of a history of inadequate safety performance and lack of formal safety procedures;

     6. Material misrepresentation. If, in the opinion of the director, there is evidence of a material misrepresentation on the contractor's prebid qualification statement; or

     7. Termination, suspension, defaults. If, in the opinion of the director, there is evidence that the contractor through its own fault has been terminated, has been suspended for cause, has been debarred from bidding, has agreed to refrain from bidding as part of a settlement or has defaulted on a contract or had a contract completed by another party.

     Sec. 5. 5 MRSA §1747, last ¶, as enacted by PL 1997, c. 295, §1, is amended to read:

     If a contractor is disqualified for any of the reasons stated in subsection 1, 2 or , 4, 5, 6 or 7, the director may disallow the contractor from bidding on any similar public improvements for a period not to exceed one year.

Effective September 21, 2001, unless otherwise indicated.

Revisor of Statutes Homepage Subject Index Search Laws of Maine Maine Legislature

About the 2001 Laws Of Maine

Previous PageTop Of PageTable Of ContentsNext Page

Office of the Revisor of Statutes
State House, Room 108
Augusta, Maine 04333

Contact the Office of the Revisor of Statutes