Previous PageTable Of ContentsNext Page

PUBLIC LAWS
First Special Session of the 122nd

CHAPTER 158
S.P. 522 - L.D. 1506

An Act To Update the Laws Governing Borrow Pits and Quarries

Be it enacted by the People of the State of Maine as follows:

     Sec. 1. 38 MRSA §484-B is enacted to read:

§484-B.     Additional standards for quarries and excavations

     In addition to other standards required by or pursuant to this article, a quarry or an excavation for borrow, clay, topsoil or silt that is licensed pursuant to this article, regardless of the date of licensing, must meet the following minimum standards concerning dust control and spill prevention.

     1. Spill prevention. Refueling operations, oil changes and other maintenance activities requiring the handling of fuels, petroleum products, hydraulic fluids and other on-site activity involving the storage or use of products that, if spilled, may contaminate groundwater, must be conducted in accordance with the department's spill prevention, control and countermeasures plan. Petroleum products and other substances that may contaminate groundwater must be stored and handled over impervious surfaces that are designed to contain spills. The spill prevention, control and countermeasures plan must be posted at the site.

     2. Dust control. Dust generated by activities at an excavation site, including dust associated with traffic to and from the excavation site, must be controlled by sweeping, paving, watering or other best management practices for control of fugitive emissions. Dust control methods may include the application of calcium chloride, as long as the manufacturer's guidelines are followed. Visible emissions from a fugitive emission source may not exceed an opacity of 20% for more than 5 minutes in any one-hour period.

     The department may require that a quarry or excavation take additional measures or provide additional information when necessary to meet the standards for development set forth in section 484.

     Sec. 2. 38 MRSA §490-A, sub-§5-A, as enacted by PL 1995, c. 700, §18, is amended to read:

     5-A. Reclamation. "Reclamation" means the rehabilitation of the area of land affected by mining, including, but not limited to, the stabilization of slopes and creation of safety benches, the planting of forests, the seeding of grasses and legumes for grazing purposes, the planting of crops for harvest and, the enhancement of wildlife and aquatic habitat and aquatic resources and the development of the site for residential, commercial, recreational or industrial use.

     Sec. 3. 38 MRSA §490-C, first ¶, as amended by PL 1995, c. 700, §23, is further amended to read:

     Except as provided in section 484-A, a person intending to create or operate an excavation under this article must file a notice of intent to comply before the total area of excavation on the parcel equals 5 or more acres excavated since January 1, 1970. Both reclaimed and unreclaimed areas are added together in determining whether this 5-acre threshold is met. A notice filed under this section must be complete, submitted on forms approved by the department and mailed to the municipality, the department, the Maine Historic Preservation Commission and each abutting property owner. The notice that is mailed to the municipality and each abutting property owner must be mailed at least 7 days prior to filing the notice of intent to comply with the regulator. The notice that is mailed to the regulator must be sent by certified mail, return receipt requested. Upon receiving the postal receipt, the owner or operator may commence operation. The municipality where the proposed excavation is located may submit comments to the department if the proposed excavation may pose an unreasonable adverse impact under the standards in section 490-D. Within 30 days of receipt of the notice of intent to comply, the department must respond to the comments made by the municipality. Abutting property owners, the Maine Historic Preservation Commission or other interested persons may submit comments directly to the department.

     Sec. 4. 38 MRSA §490-D, sub-§§6-A, 7 and 8, as amended by PL 1995, c. 700, §24, are further amended to read:

     6-A. Public and private roads. A natural buffer strip must be maintained between the working edge of an excavation and a road or right-of-way as follows.

Except for paragraph B, the department may not grant a variance from the provisions of this subsection. The department may grant a variance from paragraph B, provided that if the variance will not result in the natural buffer strip being reduced to less than 50 feet between the working edge of the excavation and any road or right-of-way, whichever is farther from the excavation, and provided that if the owner or operator installs visual screening and safety measures as required by the department.
A distance specified in this subsection is measured from the outside edge of the shoulder of the road or edge of the right-of-way unless otherwise specifically provided.

     7. Property boundary. A natural buffer strip at least 50 feet wide must be maintained between any excavation and any property boundary. A natural buffer strip at least 25 feet wide must be maintained between any topsoil excavation and a property boundary. These distances may be reduced to not less than 10 feet with the written permission of the affected property owner or owners, except that the distance may not be reduced to less than 25 feet from the boundary of a cemetery or burial ground. The buffer strip between excavations owned by abutting owners may be eliminated with the abutter's written permission, provided the elimination of this buffer strip does not increase the runoff from either excavation across the property boundary. Any written permission to reduce a buffer must provide that it remains in effect until mining ceases and must be recorded in the registry of deeds. All property boundaries must be identified in the field by markings such as metal posts, stakes, flagging or blazed trees. The department may not grant a variance from the provisions of this subsection.

     8. Erosion and sedimentation control. All reclaimed and unreclaimed areas, except for access roads, must be naturally internally drained at all times unless a variance is obtained from the department.

The department may grant a variance from this subsection, except for paragraphs C, D and E. Areas are not considered "naturally internally drained" if surface discharge is impeded through the use of structures such as detention ponds, retention ponds and undersized culverts.

     Sec. 5. 38 MRSA §490-D, sub-§9, as amended by PL 1995, c. 700, §24, is repealed and the following enacted in its place:

     9. Water quality protection and storm water management. Standards of the laws governing storm water management and waste discharge must be met as provided in this subsection.

     Sec. 6. 38 MRSA §490-D, sub-§13, as amended by PL 1995, c. 700, §24, is further amended to read:

     13. Dust. Dust generated by activities at the excavation site, including dust associated with traffic to and from the excavation site, must be controlled by sweeping, paving, watering or other best management practices for control of fugitive emissions. Dust control methods may include the application of calcium chloride, providing the manufacturer's labeling guidelines are followed. The department may not grant a variance from the provisions of this subsection. Visible emissions from a fugitive emission source may not exceed an opacity of 20% for more than 5 minutes in any one-hour period.

     Sec. 7. 38 MRSA §490-J, sub-§2, ¶¶A and B, as amended by PL 1995, c. 700, §31, are further amended to read:

     2. Annual fee. By March 1st of each year, an annual fee of:

     Sec. 8. 38 MRSA §490-N is enacted to read:

§490-N. Release

     The department may grant a release from the requirements of this article to the owner or operator or a transferee after reclamation of the affected area as determined by the department. The department shall inspect the site before making this determination. The release will terminate if any further excavation on the parcel for borrow, clay, topsoil or silt is proposed by the owner or operator or a transferee. A person proposing further excavation on the parcel must file a notice of intent to comply pursuant to section 490-C and comply with all requirements of this article. Payment of the annual fee under section 490-J will resume in the year when the further excavation begins.

     Sec. 9. 38 MRSA §490-W, sub-§18, as enacted by PL 1995, c. 700, §35, is amended to read:

     18. Reclamation. "Reclamation" means the rehabilitation of the area of land affected by mining, including, but not limited to, the stabilization of slopes and creation of safety benches, the planting of forests, the seeding of grasses and legumes for grazing purposes, the planting of crops for harvest and, the enhancement of wildlife and aquatic habitat and aquatic resources and the development of the site for residential, commercial, recreational or industrial use. "Reclamation" does not include the filling in of pits and the filling or sealing of shafts and underground workings with solid materials unless necessary for the protection of groundwater or for reasons of safety.

     Sec. 10. 38 MRSA §490-Y, first ¶, as amended by PL 1997, c. 364, §22, is further amended to read:

     Except as provided in section 484-A, a person intending to create or operate a quarry under this article must file a notice of intent to comply before the total area of excavation of rock or overburden on the parcel exceeds one acre. Both reclaimed and unreclaimed areas are added together in determining whether this one-acre threshold is exceeded. A notice filed under this section must be complete, submitted on forms approved by the department and mailed to the municipality where the quarry is located, the department, the Maine Historic Preservation Commission and each abutting property owner. The notice that is mailed to the municipality and each abutting property owner must be mailed at least 7 days before the notice of intent to comply is filed with the regulator. The notice that is mailed to the department must be sent by certified mail, return receipt requested. Upon receiving the postal receipt, the owner or operator may commence operation of the quarry. The municipality where the proposed quarry is located may submit comments to the department if the proposed quarry may pose an unreasonable adverse impact under the standards in section 490-Z. Within 30 days of receipt of the notice of intent to comply, the department shall respond to the comments made by the municipality. Abutting property owners, the Maine Historic Preservation Commission or other interested persons may submit comments directly to the department.

     Sec. 11. 38 MRSA §490-Z, sub-§3, as enacted by PL 1995, c. 700, §35, is amended to read:

     3. Groundwater protection. To ensure adequate groundwater protection, the following setback requirements must be met.

The department may grant a variance from the provisions of paragraph C upon consultation with the person or entity that controls the public drinking water supply affected by the excavation. The department may not grant a waiver from the provisions of paragraph A, B or D.
Excavation below the seasonal high water table of an area previously designated for potential use as a public drinking water source by a municipality or private water company is prohibited. The department may grant a variance allowing excavation below the seasonal high water table if the applicant demonstrates that the yield of groundwater flow to protected waters or wetlands or public drinking water sources or private drinking water supplies will not be adversely affected by the excavation.
In the event of excavation below the seasonal high water table, the operator of a mining activity that affects by excavation activities a public drinking water source or private drinking water supply by contamination, interruption or diminution must restore or replace the affected water supply with an alternate source of water, adequate in quantity and quality for the purpose served by the supply. This provision is not intended to replace any independent action that a person may have whose water supply is affected by a mining activity.

     Sec. 12. 38 MRSA §490-Z, sub-§§6, 7 and 8, as enacted by PL 1995, c. 700, §35, is amended to read:

     6. Roads. A natural buffer strip must be maintained between the working edge of an excavation and a road or right-of-way as follows.

The department may not grant a variance from the provisions of paragraph A or C. The department may grant a variance from paragraph B if the variance does not result in the natural buffer strip being reduced to less than 50 feet between the working edge of the excavation and any road or right-of-way, whichever is farther from the excavation, and if the owner or operator installs visual screening and safety measures as required by the department.
A distance specified in this subsection is measured from the outside edge of the shoulder of the road or edge of the right-of-way unless otherwise specifically provided.

     7. Property boundary. A natural buffer strip at least 100 feet wide must be maintained between an excavation and any property boundary. This distance may be reduced to 10 feet with the written permission of the affected abutting property owner or owners, except that the distance may not be reduced to less than 25 feet from the boundary of a cemetery or burial ground. The natural buffer strip between quarries owned by abutting owners may be eliminated with the abutter's written permission if the elimination of this natural buffer strip does not increase the runoff from either excavation across the property boundary. Any written permission to reduce a buffer must provide that it remains in effect until mining ceases and must be recorded in the registry of deeds. All property boundaries must be identified in the field by markings such as metal posts, stakes, flagging or blazed trees. The department may not grant a variance from the provisions of this subsection.

     8. Erosion and sedimentation control. All reclaimed and unreclaimed areas, except for access roads, must be naturally internally drained at all times unless a variance is obtained from the department. Stockpiles consisting of topsoil to be used for reclamation must be seeded, mulched or otherwise temporarily stabilized.

The department may not grant a variance from the provisions of paragraph A, B or C. Areas are not considered "naturally internally drained" if surface discharge is impeded through the use of structures such as detention ponds, retention ponds and undersized culverts.

     Sec. 13. 38 MRSA §490-Z, sub-§9, as enacted by PL 1995, c. 700, §35, is repealed and the following enacted in its place:

     9. Water quality protection and storm water management. Standards of the laws governing storm water management and waste discharge must be met as provided in this subsection.

     Sec. 14. 38 MRSA §490-Z, sub-§12, as enacted by PL 1995, c. 700, §35, is amended to read:

     12. Dust. Dust generated by activities at a quarry, including dust associated with traffic to and from a quarry, must be controlled by sweeping, paving, watering or other best management practices for control of fugitive emissions. Dust control methods may include calcium chloride as long as the manufacturer's labeling guidelines are followed. The department may not grant a variance from the provisions of this subsection. Visible emissions from a fugitive emission source may not exceed an opacity of 20% for more than 5 minutes in any one-hour period.

     Sec. 15. 38 MRSA §490-Z, sub-§14, ¶F, as enacted by PL 1995, c. 700, §35, is amended to read:

     Sec. 16. 38 MRSA §490-EE, sub-§3, ¶B, as enacted by PL 1995, c. 700, §35, is amended to read:

     Sec. 17. 38 MRSA §490-FF is enacted to read:

§490-FF. Release

     The department may grant a release from the requirements of this article to the owner or operator or a transferee after reclamation of the affected area as determined by the department. The department shall inspect the site before making this determination. The release will terminate if any further excavation on the parcel is proposed by the owner or operator or a transferee. A person proposing further excavation on the parcel must file a notice of intent to comply pursuant to section 490-Y and comply with all requirements of this article. Payment of the annual fee under section 490-EE will resume in the year when the further excavation begins.

Effective September 17, 2005.

Revisor of Statutes Homepage Subject Index Search 122nd Laws of Maine Maine Legislature

About the 1st Regular & 1st Special Session Laws Of Maine

Previous PageTop Of PageTable Of ContentsNext Page

Office of the Revisor of Statutes
State House, Room 108
Augusta, Maine 04333

Contact the Office of the Revisor of Statutes