§3133-A.__Significant agreements and contracts relating to

 
generating capacity or energy capacity prohibited

 
without prior order of the commission

 
Sec. 5. 35-A MRSA §3133-A, sub-§2, as amended by PL 1995, c. 357, §7,
is further amended to read:

 
2. Definitions. As used in this section, unless the context
indicates otherwise, the following terms have the following
meanings.

 
A. "Significant agreement or contract" means a contract or
other agreement enforceable as a contract that binds the
utility to a future course of action with respect to
supplying, purchasing, dispatching or exchanging generating
capacity, or energy or transmission capacity or any renewal,
amendment or extension of any contract or agreement that is
for a period of longer than 3 years and involves one of the
following, whichever is less:

 
(1) More than 5,000 kilowatts of electrical generating
capacity, or 50,000,000 kilowatt hours or more of
energy per year, flowing over a transmission line with
a capacity greater than 100 kilovolts;

 
(2) More than 10% of the generating capacity, transmission
capacity or energy generation of the utility; or

 
(3) More than 1.0% of the total annual kilowatt hour
sales of the utility.

 
SUMMARY

 
This bill repeals requirements that electric utilities obtain
certificates of public convenience and necessity from the Public
Utilities Commission before constructing or modifying
transmission lines or contracting for transmission line capacity.