| 3.__Review of plan.__The commissioner shall review the pollution |
prevention plan of a facility when, in the commissioner's judgment, |
the plan summary indicates significant deficiencies in the |
pollution prevention efforts at the facility or when the facility |
fails to reach any of its reduction goals by more than 25%, as |
indicated in the plan summary.__The commissioner may require the |
owner or operator of a facility to make any modifications to a |
pollution prevention plan necessary for compliance with this |
chapter.__In reviewing a pollution prevention plan, the |
commissioner has the authority to require the owner or operator of |
the facility to provide information the commissioner finds |
necessary to analyze the reviewed document.__If the commissioner |
requires the owner or operator of the facility to modify a |
pollution prevention plan, the commissioner shall allow a |
reasonable time period of not less than 90 days for the |
modifications to be made and shall consider the financial impact of |
the changes or modifications on the owner or operator of the |
facility.__The owner or operator of a facility may appeal to the |
board a decision of the commissioner to require the owner or |
operator to modify a pollution prevention plan under this |
subsection or subsection 4. |