| | 1.__Plan summary.__The commissioner may require the owner or | operator of a facility to submit a summary of the pollution | prevention plan required under section 2305 within 60 days when: |
|
| A.__A facility has not made sufficient progress in reducing | toxics use, toxics release or hazardous waste generation as | evidenced by the facility's progress report; or |
|
| B.__A new facility has toxics use, toxics release or | hazardous generation rates that are significantly greater | per unit of product than in similar facilities within the | same standard industrial code category. |
|
| A plan summary submitted to the commissioner pursuant to this | subsection must include the evaluation methods used, the findings | and conclusions and the implementation schedule.__An owner or | operator may designate information in a plan summary__as | confidential under section 1310-B. |
|
| The commissioner may review a plan summary, pursuant to | subsection 2, and require the owner or operator of a facility to | make any modifications to the plan summary necessary for | compliance with this chapter. |
|
| | 2.__Review of plan summary.__In reviewing the adequacy of a | plan summary, the commissioner shall base a determination on | whether the plan summary is complete and prepared in accordance | with the facility goals and guidelines established pursuant to | this chapter.__In reviewing a plan summary, the commissioner has | the authority to require the owner or operator of the facility to | provide information the commissioner finds necessary to analyze | the reviewed document. |
|
| If the commissioner determines that a plan summary is inadequate, | the commissioner shall notify the owner or operator of the | facility of the inadequacy, identifying the specific | deficiencies.__The commissioner may specify a reasonable time | period of not less than 90 days within which the owner or | operator of the facility must submit a modified plan summary | addressing the specified deficiencies.__The commissioner may, | upon request, provide technical assistance, if available, to aid | the owner or operator of the facility in modifying the plan | summary. |
|
| If the commissioner determines that a modified plan summary is | inadequate, the commissioner may either require further | modification or assess fees as provided in section 2313.__If a | generator fails to submit a modified plan summary within the | required time period, the commissioner may assess additional fees | as established in section 1319-I, subsection 2-A. |
|
|