| E. Statement of yield goals for land receiving farm | nutrients; and |
|
| F. Additional information established through rulemaking.; |
|
| G.__Site-specific dates recommended for the spreading of | manure and spraying or irrigation of liquid manure.__In | compliance with section 4207, the plan may not recommend | spreading between December 1st of a calendar year and March | 15th of the following calendar year; and |
|
| H.__A recommended timetable for implementing the plan. |
|
| | 2. Farms requiring a nutrient management plan. A farm that | meets one or more of the following criteria is required to have a | nutrient management plan: |
|
| A. A farm that confines and feeds 50 or more animal units | at any one time; |
|
| B. A farm that utilizes more than 100 tons of manure per | year not generated on that farm; |
|
| C. A farm that, after December 1, 1998, is the subject of a | verified complaint of improper manure handling; or |
|
| D. A farm that stores or utilizes regulated residuals. |
|
| | 3. Responsibility of person preparing nutrient management | plans. Upon completion of a nutrient management plan, a person | certified to prepare nutrient management plans in accordance with | this chapter shall notify the department. The notification must | include the name and address of the owner or operator of the farm | and the location of the farm for which the plan was prepared. A | person preparing a nutrient management plan required by this | chapter shall adhere to rules adopted in accordance with this | chapter pertaining to the preparation and requirements of the | plan. |
|
| | 4. Compliance date for farms operational on March 31, 1998. | Notwithstanding the provisions of subsections 1 to 3, Except for | a farm requiring a livestock operations permit under section | 4205, an owner or operator of a farm that is was operational on | the effective date of this chapter March 31, 1998 and meets the | criteria established in subsection 2, paragraph A, or B or D is | not required to shall have a nutrient management plan prepared | for that farm until no later than January 1, 2001. A nutrient | management plan must be prepared in accordance with this chapter | no later than January 1, 2001. The Except as provided in | subsection 8, the plan must be implemented no later than October | 1, 2005 2007. |
|
|