LD 1633
pg. 1
LD 1633 Title Page An Act to Clarify Rights of Retainage in Public Construction Contracts Page 2 of 2
Download Bill Text
LR 1318
Item 1

 
Be it enacted by the People of the State of Maine as follows:

 
Sec. 1. 5 MRSA §1746, as amended by PL 1989, c. 483, Pt. A, §19, is
repealed and the following enacted in its place:

 
§1746. Retainage in public construction contracts

 
1.__Definitions.__As used in this section, unless the context
otherwise indicates, the following terms have the following
meanings.

 
A.__"Designer" means the architect or engineer designated by
the contract documents to design the work or to provide
contract administration for the owner.

 
B.__"Punch list" means an inventory of work that remains
deficient or incomplete after substantial completion.__
"Punch list" includes reasonable estimates of cost for
correction or completion of the work contained on the list.__
Deficiencies discovered after acceptance of the work are not
punch list items but may be covered by warranty or contract
obligations.

 
C.__"Substantial completion" is the stage in the progress of
the work when the work or designated portion of the work is
sufficiently complete in accordance with the contract
documents so the owner can occupy or utilize the work for
its intended use.

 
2.__Retainage.__In a contract awarded for a public
improvement, the public owner may retain 5% of the money due the
contractor until substantial completion of the work.__At
substantial completion, the owner and the contractor shall
inspect the work and prepare a punch list.__The owner may
thereafter withhold for defective or incomplete work only those
funds that are sufficient to account for 1 1/2 times the value of
punch list work.__As punch list work is completed, the retainage
held by the owner must be correspondingly reduced.__Funds may not
be retained in anticipation of warranty claims but may be
retained as directed by contractor's surety or as necessary to
account for liquidated damages or other contract defaults as
determined by the designer.

 
3.__Designer's role.__Issues between the contractor and the
public owner concerning substantial or final completion or
concerning the scope or cost of punch list work and any other
questions necessary to determine when retained funds are due to
be released must be promptly resolved by the designer, whose
decisions are not binding by virtue of this section for any other
purpose.


LD 1633 Title Page Top of Page Page 2 of 2