| 2.__Retainage.__In a contract awarded for a public |
| improvement, the public owner may retain 5% of the money due the |
| contractor until substantial completion of the work.__At |
| substantial completion, the owner and the contractor shall |
| inspect the work and prepare a punch list.__The owner may |
| thereafter withhold for defective or incomplete work only those |
| funds that are sufficient to account for 1 1/2 times the value of |
| punch list work.__As punch list work is completed, the retainage |
| held by the owner must be correspondingly reduced.__Funds may not |
| be retained in anticipation of warranty claims but may be |
| retained as directed by contractor's surety or as necessary to |
| account for liquidated damages or other contract defaults as |
| determined by the designer. |