A. An applicant for Tier 1 or, Tier 2 or Tier 3 review must | | shall meet the following requirements. |
|
| | | (1) Alteration of freshwater wetland areas on the | | property must be avoided to the extent feasible | | considering cost, existing technology and logistics | | based on the overall purpose of the project. |
|
| | | (2) The area of the freshwater wetland to be altered | | must be limited to the minimum amount necessary to | | complete the project. |
|
| | (3) Erosion control measures must be used to prevent | sedimentation of protected natural resources. A 25- | foot buffer strip must be maintained between the | activity and any river, stream or brook. |
|
| | (4) The activity must comply with applicable water | quality standards pursuant to section 480-D, subsection | 5. |
|
| | B. An applicant for Tier 1, Tier 2 or Tier 3 review for | projects that would alter wetland hydrology and could also | alter stream flows or other adjacent surface waters, must | comply with the water quality classification standards | contained in section 465. |
|
| | | C.__An applicant for Tier 1 review shall meet the following | | requirements. |
|
| | | (1)__Erosion control measures must be used to prevent | | sedimentation of protected natural resources.__A 25- | | foot buffer strip must be maintained between the | | activity and any river, stream or brook. |
|
| | | (2)__The activity must comply with applicable water | | quality standards pursuant to section 480-D, subsection | | 5. |
|
| | | D.__An applicant for Tier 2 or Tier 3 review shall comply | | with the standards contained in section 480-D. |
|
| | | Sec. 2. 38 MRSA §480-X, sub-§7, ķA, as enacted by PL 1995, c. 460, §7 | | and affected by §12, is amended to read: |
|
| | | A. An application form must be submitted, with the | | application fee, to the department and include the following | | information: |
|
|