| (1) Documentation that public notice has been provided | of the proposed project in accordance with department | rules; |
|
| (2) A United States Geological Survey map showing the | project location; |
|
| (3) Written certification by a knowledgeable | professional experienced in wetland science that the | project will not alter, or cause to be altered, a | wetland described in subsection 4 or 5; |
|
| (4) A top view drawing of the entire project, | including existing and proposed fill, excavation, roads | and structures; cross-sectional drawings of any fill or | excavated areas; delineation of the wetland boundaries | and calculated area of freshwater wetlands affected; | description of existing vegetation on the project site; | identification of any surface water bodies within 100 | feet of the proposed alteration; and a drawing of the | 25-foot buffer strip between the project and any river, | stream or brook; |
|
| (5) A soil erosion and sedimentation control plan; |
|
| (6) For work in previously mined peatlands, | information on the past mining activity, including the | approximate dates of the mining activity, the area and | depth to which peat has been excavated from the site, | any restoration work on the site and the current | condition of the site; |
|
| (7) A statement describing why the project can not be | located completely in upland areas and any alternatives | that exist for the project that would either avoid or | minimize the amount of proposed freshwater wetland | alteration; and |
|
| (8) A plan for compensating for lost functions and | values of the freshwater wetland when required by, and | in accordance with, rules adopted by the department.; | and |
|
| (9)__Any other information determined by the department | to be necessary to meet the requirements of section | 480-D and rules adopted by the department. |
|
|