In determining the amount of freshwater wetland to be altered, all | components of a project, including all phases of a multiphased | project, are treated together as constituting one single and | complete project. Activity authorized or legally conducted prior | to the effective date of this section is not included. |
|
| The standards of section 480-D do not apply to projects that | qualify for Tier 1 or Tier 2 review, except that water quality | standards under section 480-D, subsection 5 apply to those | projects. Projects that meet the eligibility requirements for | Tier 1 or Tier 2 review and that satisfy the permitting | requirements set forth in subsection 3, and 6 or 7, as | applicable, are presumed not to have significant environmental | impact. |
|
| | 3. General requirements. A person undertaking an activity | for which a permit is processed pursuant to this section must | shall satisfy the requirements of this subsection. |
|
| A. An applicant for Tier 1 or, Tier 2 or Tier 3 review must | shall meet the following requirements. |
|
| (1) Alteration of freshwater wetland areas on the | property must be avoided to the extent feasible | considering cost, existing technology and logistics | based on the overall purpose of the project. |
|
| (2) The area of the freshwater wetland to be altered | must be limited to the minimum amount necessary to | complete the project. |
|
| (3) Erosion control measures must be used to prevent | sedimentation of protected natural resources. A 25- | foot buffer strip must be maintained between the | activity and any river, stream or brook. |
|
| (4) The activity must comply with applicable water | quality standards pursuant to section 480-D, subsection | 5. |
|
| B. An applicant for Tier 1, Tier 2 or Tier 3 review for | projects that would alter wetland hydrology and could also | alter stream flows or other adjacent surface waters, must | comply with the water quality classification standards | contained in section 465. |
|
| C.__An applicant for Tier 1 review shall meet the following | requirements. |
|
|