Sec. B-1. 35-A MRSA §3210-C, sub-§1, ¶A-1  is enacted to read:

A-1.  "Contract for differences" means a contractual arrangement between a buyer and a seller in which cash payments are made based on the actual or relative difference between a target price for energy or a capacity resource and the market value of the energy or capacity resource. Under a contract for differences, the seller pays to the buyer the positive difference between the market value and the target price and the buyer pays to the seller the negative difference between the market value and the target price. "Contract for differences" does not include a contract for the physical delivery of energy or capacity resources.

Sec. B-2. 35-A MRSA §3210-C, sub-§3,  as amended by PL 2007, c. 293, §2, is further amended to read:

3. Commission authority.   The commission may direct large investor-owned transmission and distribution utilities to enter into long-term contracts for:
A. Capacity resources; and
B. Any available energy associated with capacity resources contracted under paragraph A:

(1) To the extent necessary to fulfill the policy of subsection 2, paragraph A; or

(2) If the commission determines appropriate for purposes of supplying or lowering the cost of standard-offer service or otherwise lowering the cost of electricity for the ratepayers in the State. Available energy contracted pursuant to this subparagraph may be sold into the wholesale electricity market in conjunction with solicitations for standard-offer supply bids.

The commission may direct large investor-owned transmission and distribution utilities to enter into contracts under this subsection only as agents for their customers and only in accordance with this section. The commission may permit, but may not require, investor-owned transmission and distribution utilities to enter into contracts for differences that are designed and intended to buffer ratepayers in the State from potential negative impacts from transmission development. To the greatest extent possible, the commission shall develop procedures for long-term contracts for investor-owned transmission and distribution utilities under this subsection having the same legal and financial effect as the procedures used for standard-offer service pursuant to section 3212 for large investor-owned transmission and distribution utilities.

The commission may enter into contracts for interruptible, demand response or energy efficiency capacity resources. These contracts are not subject to the rules of the State Purchasing Agent. In a competitive solicitation conducted pursuant to subsection 6, the commission shall allow transmission and distribution utilities to submit bids for interruptible, demand response or energy efficiency capacity resources.

Capacity resources contracted under this subsection may not exceed the amount necessary to ensure the reliability of the electric grid of this State or to lower customer costs as determined by the commission pursuant to rules adopted under subsection 10.

Unless the commission determines the public interest requires otherwise, a capacity resource may not be contracted under this subsection unless the commission determines that the capacity resource is recognized as a capacity resource for purposes of any regional or federal capacity requirements.

The commission shall ensure that any long-term contract authorized under this subsection is consistent with the State's goals for greenhouse gas reduction under Title 38, section 576 and the regional greenhouse gas initiative as described in the state climate action plan required in Title 38, section 577.

Sec. B-3. 35-A MRSA §3210-C, sub-§7,  as amended by PL 2007, c. 293, §4, is further amended to read:

7. Disposition of resources.   A large An investor-owned transmission and distribution utility shall sell capacity resources and energy purchased pursuant to subsection 3 or take other action relative to such capacity resources and energy as directed by the commission.

Sec. B-4. 35-A MRSA §3210-C, sub-§8,  as enacted by PL 2005, c. 677, Pt. C, §1, is amended to read:

8. Cost recovery.   The commission shall ensure that a large an investor-owned transmission and distribution utility recovers in rates all costs of contracts entered into pursuant to subsection 3, including but not limited to any impacts on the utility's costs of capital. A price differential existing at any time during the term of the contract between the contract price and the prevailing market price at which the capacity resource is sold or any gains or losses derived from contracts for differences must be reflected in rates and may not be deemed to be imprudent.

Sec. B-5. 35-A MRSA §3210-C, sub-§10,  as enacted by PL 2005, c. 677, Pt. C, §1, is amended to read:

10. Rules.   The commission shall adopt rules to implement this section. In adopting rules, the commission shall consider the financial implications of this section on large investor-owned transmission and distribution utilities. Rules adopted under this subsection are major substantive rules as defined in Title 5, chapter 375, subchapter 2-A. The commission may not enter into or direct any large investor-owned transmission and distribution utility to enter into any contract pursuant to this section until rules are finally adopted under this subsection.